Nov. 27, 2018 – West Bend, WI – Details on the time schedule, construction sequence and notes to contractors were tacked up inside a construction trailer on site. Details below.
The 192,000-square-foot store is being built to the south of Highway 33 and just east of CTH Z.
About 30 earth movers are on site prepping the parking lot for the new store. Footings should go in within the next month and construction on the building will get underway in December 2018.
The new store should be open by September 2019.