August 22, 2019 – Kewaskum, WI – There’s been considerable progress made since the last update was posted 10 days ago regarding construction of the Wisconsin 9/11 Memorial in Kewaskum.
Brick layers from Flagstone landscaping of Cedarburg are setting white stone into place for the gallery seating area. Aerial shots paint a good picture of the outline of the park and the concrete pentagon at the center of the mall which will hold the beam of steel recovered from the North Tower of the World Trade Center.
Crews on site at Fond du Lac Avenue and First Street expect the first stage of construction to be completed by October.
Watch for regular updates at WashingtonCountyInsider.com
Click HERE for more details about the Wisconsin 9/11 Memorial.