- Howard Immel Inc from Green Bay is the Construction Manager.
- Bids for the site work, concrete and asphalt are due Sept. 20.
- Start date is listed as Oct 1, 2018.
- Completion is listed as September 9, 2019.
- 192,000-square-foot retail store
- 7,100-square-foot convenience store
- 652 parking stalls
The information posted aligns with the concept plan reviewed by the West Bend Plan Commission on August 7. Click HERE to see those details.
Fleet Farm spokesman Tom Carrico said they “haven’t really finalized the scheduling details.”
He said the information in the Daily Reporter is probably coming from construction manager Howard Immel Inc.
Plans for an exit on CTH Z
On Aug. 13, 2018 during the Town of West Bend Board meeting there was some discussion regarding Fleet Farm and how the DOT wanted an access road off CTH Z.
Fleet Farm laid out designs with the West Bend Plan Commission last week regarding its new 190,000-square-foot store on Highway 33 and County Hwy Z. During the pitch to the city Fleet officials said they would only have access roads off Highway 33. During Monday night’s Town Board meeting Town Chairman Jim Heipp said the city, state, and county are satisfied with that plan however the DOT wants an access road off County Hwy Z. That plan is still in discussion.
When Carrico was asked about an access road off County Hwy Z he said, “The plan we submitted to the city is the plan we’re going forward with; we are waiting for DOT comment.”
Plan Commission meeting Tuesday, Sept. 11
On Tuesday, Sept. 11 the West Bend Plan Commission will review several development proposals that have ties to the Fleet Farm property on W. Washington Street and CTH Z.
There will be public hearings that affects zoning changes and more details will be released on a proposed 7,162-square-foot gas station and convenience store. The proposed gas station would include 18 fuel pumps and 9 islands.
Details are posted by clicking the Public Agenda below.
2018-09-11 Plan Commission – Public Agenda-1229