July 7, 2023 – Germantown, WI – A few updates regarding the ongoing road construction in Germantown.
Eastbound County Line Rd over I-41 is scheduled to reopen the evening of Wednesday, July 5
Westbound County Line Rd over I-41 is scheduled to close the evening of Wednesday, July 5 for about 2 months
Freistadt Road bridge over I-41 is scheduled to reopen the evening of Friday, July 7, 2023.
Maple Road bridge over I-41 is scheduled to reopen the evening of Saturday, July 8, 2023.
Mequon Road bridge over I-41 (not Lannon Road which has the on/off ramps) is scheduled to close on Monday, July 10, 2023, for about 5 months
For more information about the project, go to https://projects.511wi.gov/41rehabilitation/