38.4 F
West Bend

Completion of 7th Avenue in West Bend behind schedule

November 2, 2021 – West Bend, WI – Reconstruction of Seventh Avenue in West Bend between Walnut Street and Highway 33 is a couple weeks behind schedule.

Seventh Avenue

The project which started July 6, 2021 included replacement of water main, storm sewer and sanitary sewer. Sidewalk, curb and gutter will also be included in the project.

Cast Iron Luxury Living

The cost will be north of $1.5 million.

The original target completion date was the end of October however there were issues with the sanitary and more work was needed than planned.

Seventh Avenue

According to City Engineer Max Marechal:

Nov. 1 – 5 work will be completed in front of the fire station and at the intersections of Cedar, Elm, and Hickory.

Nov. 3 – 4 the sidewalks and aprons will be formed and Friday, Nov. 5 those sections will be poured along with the median in front of the fire department. Also Thursday there will be a fine grade between the concrete and the existing asphalt. On Friday the intersections will be completed.

At the end of the week, Nov. 6 all the concrete should be finished.

Seventh Avenue

Nov. 8 – 11 restoration will be completed with grading, seeding and matting and pavement markings will be put down Thursday, November 11.

Seventh Avenue is expected to reopen November 12.

Leave a Reply

Work or the content on WashingtonCountyInsider.com cannot be downloaded, printed, or copied. The work or content on WashingtonCountyInsider.com prohibits the end user to download, print, or otherwise distribute copies.

Subscribe

FREE local news at Washington County Insider on YouTube

Related Articles