April 18, 2019 – Hartford, WI – Nearly 40 pilots and local aeronautics enthusiasts joined staff, engineers and contractors to discuss the 2019 airport expansion project plans this week at the Hartford Rec Center.
The key components to the meeting was explaining when segments of the project were to be completed and how current tenants in the airport could be expected to have their normal pathways closed down. It is the hope of the contractors the airport will only be totally shut down for up to four to six weeks during June and July.